Project Details

Project Specific Information

Project Details 

Project Name: Cranbrook School Redevelopment Project 

Consent Number: SSD 8812 

Status: Construction Phase 

Architect: Architectus 

Contractor: Richard Crookes Constructions 

Commencement: Dec 2019 

Forecast Completion: Late 2021 

Electorate: Wentworth 

Address: 5 Victoria Road, Bellevue Hill NSW 2023 

Progress Summary 

Item

Status

Archaeological testing and salvage investigations

Complete

Construction Certificate 01 – Demolition, Piling & Excavation and Construction Commencement

December 2019

Early Works

Complete

Construction Certificate 02 – AFC Inground Services and Structure

January 2020

Construction Certificate 03 – Balance of Structure for AFC and CB

October 2020

Construction Certificate 04 – All remaining works (excl. Public Domain works)

December 2020

Construction Certificate 05 – External Facades to AFC and CB

February 2021

Construction Certificate 06 – Public Domain Works

June 2021

Construction

In progress

Relevant Documents  

Below is a list of key documents pertaining to the Cranbrook Senior School Campus Masterplan 2 Renewal Project. 

EIS & RTS

Complaint Register

  • Summary of Monitoring Results of the Development 

    The site is subject of Compliance Reports and Independent Environmental Audits as per the SSD Conditions of Consent. These documents are made publicly available as required in the consent.

    D15 – D17 – Construction Noise Limits

    Richard Crookes Constructions are abiding by the noise limits outlined in the approved Construction Noise & Vibration Management Plan (CNVMP) and are monitoring noise in areas that are adjacent to sensitive receivers. Complaints are investigated and responded to in accordance with the complaints handling procedures and noise mitigation measures within the CNVMP and the Community Communication Strategy (CCS).

    D18 – D20 – Vibration Criteria

    Richard Crookes Constructions are conducting vibration monitoring during vibratory works and abiding by the limits prescribed within the above listed conditions of consent. Complaints are investigated and responded to in accordance with the complaints handling procedures and noise mitigation measures within the CNVMP and the Community Communication Strategy (CCS).

    D21 – D22 – Air Quality

    Richard Crookes Constructions are taking all reasonable steps to mitigate dust generation during construction activities. Dust monitoring is ongoing adjacent to sensitive receivers and remain within allowable limits in the Environmental Planning and Assessment (EP&A) guidelines. 

    D23 – Erosion and Sediment Control

    On-site and off-site erosion and sediment controls are being monitored daily by Richard Crookes Constructions. As works progress on-site, the erosion and sediment control are adjusted to reduce impact to Council stormwater. External erosion and sediment controls are maintained and cleaned regularly.

    Monitoring will be carried out with the relevant documents listed below:

  • Documents relating to Condition A17 & B4 – External Walls and Cladding 

    Please click here for the Letter re Facades and Cladding. 

  • Documents relating to Condition B13 – Construction Impact Assessment and Management Plan 

    Please click here for the Construction Impact Assessment and Management Plan. 

  • Documents relating to Condition C1 – Notice of Commencement 

    Please click here for the Notice of commencement. 

  • Documents relating to Condition C4 – Protection of Public Infrastructure 

    Please click here for the Dilapidation Report. 

    Please click here for the Memorandum from the Sydney Water Building Over Asset (BOA) Application. 

    Please click here for the Report from the Sydney Water Building Over Asset (BOA) Application. 

    Please click here for the Technical Guidelines from the Sydney Water Building Over Asset (BOA) Application. 

  • Documents relating to Conditions C6 & C7 – Community Communications Strategy 

    Please click here for the Community Communications Strategy. 

    Please click here for the DPIE approval letter.

  • Documents relating to Condition C8 – Rainwater Harvesting 

    Please click here for the Rainwater Re-Use Plan. 

  • Environmental Management Plan (CEMP) & Sub-Plans 

    Please click here for the Construction Environmental Management Plan. 

    Please click here for the Construction Traffic and Pedestrian Management Sub-Plan. 

    Please click here for the Construction Noise and Vibration Management Sub-Plan. 

    Please click here for the Construction Waste Management Sub-Plan. 

    Please click here for the Construction Soil and Water Management Sub-Plan. 

    Please click here for the Flood Emergency Response Sub-Plan. 

    Please click here for the Unexpected Finds Protocol for contamination, Unexpected Finds Protocol for Aboriginal and non-Aboriginal heritage, Waste Classification and Validation. 

  • Documents relating to Conditions C25, C26, C27 & C28 – Compliance Reporting

    Please click here for the Pre-Construction Compliance Report

    Please click here for the Construction Compliance Report 01

    Please click here for the Construction Compliance Report 02

    Please click here for the Construction Compliance Report 03

  • Documents relating to Condition D31, D32, D33, D34, D35 & D36 – Independent Environmental Audit

    Please click here for the Independent Audit Program.

    Please click here for the DPIE Approval of Independent Auditor.

    Please click here for the Independent Environmental Audit Report 01 

    Please click here for the Response to Environmental Audit Report 01 

    Please click here for the Independent Environmental Audit Report 02

    Please click here for the Response to Environmental Audit Report 02

    Please click here for the Independent Environmental Audit Report 03

    Please click here for the Response to Environmental Audit Report 03