Masterplan Update Week 4, Term 2 - Cranbrook School

Masterplan Update Week 4, Term 2

12 May 21 by Natalie Cook

Due to the inclement weather recently, RCC have made slower than usual progress. 

The Aquatic & Fitness Centre below ground works have predominately comprised completion of Level B2 concrete slabs, waterproofing prior to formwork and reinforcement of concrete slabs.  We have now reached approximately 40% coverage of the AFC carpark roof slab and reinforcement of the AFC main pool beams.

Regarding progress for the Centenary Building, works included completion of the Level 2 slabs, Level 3 eastern slab, formwork on the western side of Level 3, steel transfer truss supports installed and commence of steel transfer truss installation. 

It’s very exciting to see the form of the building taking shape and the great progress happening on site, despite the inclement weather.